UD Worrilow
Two (2) 30,000 CFM AHU with thermal break construction. Location University of Delaware Challenge Aggressive lead time with high-end performance. A design challenge for high-end laboratory-type applications. Solution ⦁ Worked within design constraints. ⦁ Flex Air manufactured unit to prevent exterior condensation. ⦁ Delivering tight tolerance on humidity and filtration/air quality. ⦁ Including energy recovery.
IPS Sofie
A 2700 sqft. custom mechanical platform and penthouse with an integrated chilled water system, hot water system, compressed air, steam, general and lab air handlers. Location Totowa, New Jersey Challenge Integrate all systems (mechanical) with limited interference to the building. Solution ⦁ Fully integrated. ⦁ Complete offsite build which allowed for reduced onsite labor and […]
WVU Ruby
A 30,000 CFM hospital-grade, rooftop AHU. Location West Virginia University Challenge The hospital was looking to replace operating room AHU with little downtime. Solution ⦁ Flex Air developed AHU custom shipping splits. ⦁ Custom down length of AHU so install could be moved via freight elevators. ⦁ Complete assembly (did not have to build on-site) […]
Allegheny Health
A 42,500 CFM hospital-grade AHU matching the architectural building siding. Location Jefferson Hills, PA Challenge Design and Build a custom AHU for exterior design to blend with the existing building. Solution ⦁ Standard construct design allowed for any number of architect siding to be factory mounted with minimal cost or lead time impact. ⦁ Custom […]
GM Ramos
Large scale manufacturing facility with over 2,200,000 CFM deployed across 42 custom outdoor, direct-fired heating, and chilled water cooling units. All the power, controls, and piping were complete for single-point connection by the installing contractor. Location Ramos, Mexico Solution ⦁ An engineered common solution to simplify production to meet the project schedule. ⦁ Worked with […]
FCA WS/WL MACK
A total of 3.3 Million CFM – (53) AHU for a large-scale new paint shop building. Designing efficient and effective filtering and conditioning for paint process. Location Detroit Challenge Size and scope of the project with an aggressive project schedule. Solution ⦁ Design and deliver AHU for the first large-scale paint shop. ⦁ Worked closely […]